Rolem
Project details
Field: Automotive
Location: Brasov
Year: 2017

ROLEM
NBHX Rolem, part of NBHX Trim Group, a world leader in the production of innovative surfaces for the automotive industry. With a tradition of over 25 years in Brașov County, the company produces ornamental parts made of noble veneer, aluminum, carbon or lacquered plastic for the interiors of luxury cars.
ROLEM
The need to expand and develop production capacity resulted in the construction of a new hall with production, storage and administrative spaces, industrial platforms and roads within the premises.
1. Project objective
Similar to the construction of the first NBHX Rolem hall in Industrial Park Brasov, ICCO Instal carried out the technical design and electrical and mechanical installation works of the hall, and its connection to the existing utilities of the industrial park.
- Fire extinguishing installations, indoor hydrants, pumping group
- External sewage and water networks
- External sewage and water networks
- Heating installations with air heaters and radiators, including central heating
- Stormwater drainage systems
- Lighting installations
- Electrical power installations, general and secondary switchboards
- Transformer station and medium voltage room
2. Challenges and solutions implemented
Automatic fire extinguishing system with sprinklers on each area. The storage area is covered with ESFR K240 sprinklers, the production area is served by two distinct ACS and protected with K160 sprinklers, and the administrative area is served by K80 sprinklers. The automatic fire protection option was chosen, with sprinklers on the entire surface of the built area, to offer the client flexibility in the layout of the spaces.
For air conditioning, the solution chosen was to install a VRV system, mounted in the coffered ceiling, unlike phase 1 of the project, where classic, bi-split devices were installed. The VRV air conditioning variant offers the client an aesthetic solution, integrated into the interior architecture, and great comfort. In addition to those listed above, the system contributes to reducing the building's energy consumption, replacing the classic heating system in the transitional seasons.
Construction of the electricity supply installation in the industrial park's transformer station, equipping local transformer stations with state-of-the-art medium voltage transformers and cells.
Achieving efficient energy distribution by equipping with general switchboards and secondary distribution boards.
An improvement over the initial project, the existing M1 hall: it was decided to create lighting in the production and storage area with a distribution system through an encapsulated bar, an easily configurable, modern system with easy possibilities for modifications.
3. Benefits for Rolem
A modern, multifunctional and versatile space, made available to the beneficiary within the agreed execution period.
The construction of the connecting body was a particularly difficult task, as the execution took place without interrupting production in the existing hall, without interrupting utilities, and without affecting the technological process.
Personalization of spaces, according to the beneficiary's requirements, right from the execution stage.
4. ICCO Instal's expertise in this project
ICCO Instal's expertise as a general installation contractor, with a complete portfolio and capacity to carry out large "design & build" projects.